Authority Monitoring Report 2021 to 2022

9. Housing

The AMR must report on policies that specify an annual number of net additional dwellings or additional affordable dwellings within the Council area. This includes completions, demolitions and outstanding commitments.

The legacy areas monitored and reported on housing data differently and this has led to variations in how this data is presented within this AMR. For more housing information, see Appendix 1 - Housing 2021/22 (.XLSX, 25.6 KB)

We will ensure that data will be presented consistently in future AMRs.

9.1 Performance against current targets

9.1.1 North & Central Areas

The annual local housing requirement target is 1430 dwellings per annum. In the monitoring year, the delivery against this housing target was 1479 (103%).

9.1.2 East Area

The annual local housing requirement target is 350 dwelling per annum. In the monitoring year, the delivery against this housing target was 222 (63%).

9.1.3 South Area

The annual local housing requirement target is 433 dwelling per annum. In the monitoring year, the delivery against this housing target was 277 (64%).

9.1.4 West Area

The housing requirement is 10,925 dwellings over the plan period 2013 to 2033.

The annualised requirement target is 546.25 dwellings per annum. In the monitoring year, the delivery against this housing target was 639 (117%).

9.2 Housing delivery test

The Housing Delivery Test (HDT) is an annual measurement of housing delivery and compares the net homes delivered over the previous 3 financial years to the homes required over the same period.

The 2022 HDT has not yet been published. It will be published on the Housing Delivery test page once available.

Due to the Covid-19 pandemic and the temporary disruption to local authority planning services and the construction sector, the number of homes required in 2019/20 was reduced by one month and in 2020/21 by four months.

9.3 Annual Housing Completions since 2012

Year Aylesbury Wycombe Chiltern South Bucks
2012/13 934 223 Not applicable 226
2013/14 990 266 148 142
2014/15 1355 423 114 139
2015/16 1191 376 158 80
2016/17 1309 788 221 411
2017/18 1395 551 286 299
2018/19 1758 814 353 328
2019/20 1715 366 130 98
2020/21 1357 357 147 121
2021/22 1479 639 222 277
Total 13,483 4803 1779 2121

9.4 Completions and demolitions

9.4.1 North & Central Areas

Table 2 Net completions including permitted development within the North & Central Areas
Net completions (brownfield) Net completions (greenfield) Net completions (not specified) Total net completions Of which is office to residential permitted development (PD) Of which is storage to residential PD Of which is light industrial to residential PD Of which is other to residential PD
Aylesbury Area 83 280 Not applicable 363 3 0 0 0
Buckingham 18 116 Not applicable 134 0 0 0 0
Winslow 1 48 Not applicable 49 0 0 0 0
Wendover 1 3 Not applicable 4 0 0 0 0
Haddenham 2 106 Not applicable 108 0 0 0 0
Rest of Rural Areas 125 696 Not applicable 821 87 0 0 0
Total 230 1249 Not applicable 1479 90 0 1 1

Major housing development is defined in the National Planning Policy Framework as “development where 10 or more homes will be provided, or the site has an area of 0.5 hectares or more”.

Table 3 Major development completions within the North & Central Areas
Major Development Completions
Aylesbury Area 341
Buckingham 126
Winslow 46
Wendover 0
Haddenham 105
Rest of Rural Areas 720
Total 1338
Table 4 Dwelling type gross completions and number of bedrooms within the North & Central Areas
Dwelling Type: House Dwelling Type: Flat Bedrooms per dwelling: 1 Bedrooms per dwelling: 2 Bedrooms per dwelling: 3 Bedrooms per dwelling: 4 Bedrooms per dwelling: 5+
1169 331 209 361 544 386 Not applicable

There were 11 demolitions of permanent dwellings within the North & Central Areas.

9.4.2 East Area

Table 5 Net completions including permitted development within the East Area
Net completions (brownfield) Net completions (greenfield) Net completions (not specified) Total net completions Of which is office to residential permitted development (PD) Of which is storage to residential PD Of which is light industrial to residential PD Of which is other to residential PD
Amersham Not applicable Not applicable 36 36 29 0 0 0
Little Chalfont Not applicable Not applicable 2 2 0 0 0 0
Chesham Not applicable Not applicable 94 94 14 0 0 2
Chalfont St Peter Not applicable Not applicable 7 7 0 0 0 0
Chalfont St Giles Not applicable Not applicable 15 15 0 0 0 0
Great Missenden/Prestwood Not applicable Not applicable 21 21 0 0 0 0
Holmer Green Not applicable Not applicable 0 0 0 0 0 0
Penn/Knotty Green Not applicable Not applicable 10 10 0 0 0 0
Chesham Bois Not applicable Not applicable 3 3 0 0 0 0
Other Green Belt Villages Not applicable Not applicable 34 34 0 0 0 0
Total Not applicable Not applicable 222 222 43 0 0 2

There were two major development completions in Amersham (24 dwellings) and Chesham (41 dwellings).

There were 46 demolitions of permanent dwellings within the East Area.

9.4.3 South Area

Table 6 Net completions including permitted development within the South Area
Net completions (brownfield) Net completions (greenfield) Net completions (not specified) Total net completions Of which is office to residential permitted development (PD) Of which is storage to residential PD Of which is light industrial to residential PD Of which is other to residential PD
Beaconsfield Not applicable Not applicable 27 27 0 0 0 0
Gerrards Cross Not applicable Not applicable 88 88 0 0 0 0
Burnham Not applicable Not applicable 79 79 0 0 0 0
Iver Not applicable Not applicable 46 46 0 0 0 0
Iver Heath Not applicable Not applicable 0 0 0 0 0 0
Taplow Not applicable Not applicable 21 21 0 0 0 0
Stoke Poges Not applicable Not applicable 2 2 0 0 0 0
Wexham Not applicable Not applicable 3 3 0 0 0 0
Denham Not applicable Not applicable 0 0 0 0 0 0
Farnham Royal Not applicable Not applicable 0 0 0 0 0 0
Other Green Belt Villages Not applicable Not applicable 11 11 0 0 0 0
Total Not applicable Not applicable 277 277 0 0 0 0

There were a number of major development completions in Gerrards Cross (50), Burnham (67), Iver (33), and Taplow (12).

There were 49 demolitions of permanent dwellings within the South Area.

9.4.4 West Area

Table 7 Net completions including permitted development within the West Area
Net completions (brownfield) Net completions (greenfield) Net completions (not specified) Total net completions Of which is office to residential permitted development (PD) Of which is storage to residential PD Of which is light industrial to residential PD Of which is other to residential PD
Tier 1: High Wycombe 380 70 Not applicable 450 60 0 0 0
Tier 2: Marlow, Princes Risborough, Bourne End/Wooburn 50 0 Not applicable 50 28 0 0 1
Tier 3: Flackwell Heath & Lane End -5 0 Not applicable Not applicable 1 0 0 0
Tier 4: Longwick 2 56 Not applicable 58 0 0 0 0
Tiers 5, 6 & Rural Areas 75 11 Not applicable 86 62 0 0 1
Total 502 137 Not applicable 639 151 0 0 2
Table 8 Major development completions within the West Area
Major Development Completions
Tier 1: High Wycombe 379
Tier 2: Marlow, Princes Risborough, Bourne End/Wooburn 16
Tier 3: Flackwell Heath & Lane End -14
Tier 4: Longwick 55
Tiers 5, 6 & Rural Areas 61
Total 497
Table 9 Dwelling type gross completions and number of bedrooms within the West Area
Dwelling Type: House Dwelling Type: Flat Bedrooms per dwelling: 1 Bedrooms per dwelling: 2 Bedrooms per dwelling: 3 Bedrooms per dwelling: 4 Bedrooms per dwelling: 5+
Tier 1: High Wycombe 151 340 191 160 70 61 9
Tier 2: Marlow, Princes Risborough, Bourne End/Wooburn 10 42 19 25 6 0 2
Tier 3: Flackwell Heath & Lane End 27 3 2 21 5 2 0
Tier 4: Longwick 58 0 0 7 21 28 2
Tiers 5, 6 & Rural Areas 31 60 40 20 13 14 4
Total 277 445 252 233 115 105 17

There were 83 demolitions of permanent dwellings within the West Area.